Northwest Freeway Municipal Utility District (Northwest Freeway MUD) has been responsible for providing water, sanitary sewer, infrastructure, and services for nearly 48 years. Northwest Freeway MUD serves approximately 4100 residents in approximately 1183 homes within the Ranch Country, Ranch Country Estates and Cypresswood Trails neighborhoods. Northwest Freeway MUD currently operates and maintains two (2) water plants with onsite water wells, one (1) wastewater treatment plant, and one (1) sanitary sewer lift station. The current infrastructure is connected by 10.9 miles of water lines, 13.4 miles of sanitary sewer lines, 1.7 miles of drainage ditches, and 6.8 miles of storm sewer lines.

On May 1st, residents of the District will be asked to vote in an election to determine whether the MUD will be authorized to issue bonds in several increments over time, as needed, to fund the maintenance, rehabilitation and upgrade of portions of the MUD's Water, Sewer, and Drainage infrastructure as it ages.

Aging Infrastructure

As the MUD’s Water, Sewage and Drainage (WS&D) continues to age, it requires regular maintenance, rehabilitation and in some cases, replacement as part of its lifecycle. In order to serve our communities properly, the MUD needs to maintain, repair, and replace infrastructure.

As a part of the Bond Election Report submitted by the District engineer, the MUD has identified some of the projects that will necessary over the next 5-10 years to maintain, replace, or upgrade the aging infrastructure owned and operated by the District. 

Long Term Plan

 Northwest Freeway MUD’s Board of Directors has worked with its engineering and financial advisors to develop a long-term plan to address the needs of the District over the coming years.

Additionally, to the needed maintenance, rehabilitation, and possible replacement to District infrastructure, a portion od this authorization will be utilized to pay for infrastructure that will service the 108 – acre annexation tract of land to be developed. The Developer reimbursement for these infrastructure costs is currently expected to be approximately $8,960,00 including non-construction, “soft” cost of issuance.

Developer reimbursements such as this are typically not paid until the taxable property valuation on the ground pays for itself, so bonds sold to fund this infrastructure would not increase the tax rate or burden on existing residents of Northwest Freeway MUD, and will add more property owners contributing to the overall tax base and revenue collection of the District.

The District’s Engineer has estimated the combined amount of bonds required to fund the above items, including inflation and net of the District’s existing authorization, to be $18,155,000.

Bond Financing vs “Pay as You Go” with Cash

The two primary options available to the MUD for funding are (1) to spread the costs of the projects out over time through the issuance of bonds or (2) to pay for the projects with cash using a "pay as you go" approach requiring substantial increases in water and sewer bills. The District must have funds in hand before it can proceed with a required project. Funding projects with maintenance taxes or water and sewer rates would likely require an increase in rates in the short-term to collect the required funds. This method places the financial burden for long term projects on current residents and could create delays and increase costs for the completion of large projects.

Authorizing the District to issue bonds would allow the Board to spread the costs of the necessary projects over numerous years and avoid the increases in maintenance tax rates and/or water and sanitary sewer rates typically required by a "pay as you go" approach. This method spreads the cost for these projects among both current and future residents and businesses in the District and enables the District to complete necessary projects quickly.

Dark ModeLight Mode